Michael’s Toyota of Bellevue required more space for their auto inventory. At 210,000 square feet, this four level garage effectively contains 675 parking stalls. Constructed as an “all precast” design, both the structural framework and floor system were fabricated off-site and delivered just-in-time for erection.
Accelerated Construction Schedule – Precast components were fabricated concurrently with site and foundation work.
Uninterrupted Business – The owner was able to continue their daily operations during every phase of work.
Double Tees – 160 pcs. – 24”deep Double Tees
Double Tees – 86 pcs. – 28” deep Double Tees
Spandrels – 67 pcs. – load bearing and non-load bearing Spandrels
Columns – 22 pcs. – 20” square & 24” square Columns
Inverted Tee Beams – 27 pcs. – 34”x40” Inverted Tee Beams