HOME North Creek Tech Center - Bothel, WA

North Creek Offic Building

This complex of upscale office buildings geared toward high tech tenants incorporates high quality prestressed concrete piles in the foundation to carry the building loads down through the soil, and provide seismic resistance.

Piling up to 80 feet long have been fabricated and shipped to the site by truck.

Products

Foundation Piles - 12" Square Prestressed Piling - 1,600 pieces


12 in. pile production

Credits

Owner Schnitzer Northwest
Designer DCI Engineers - Civil/Structural
GeoEngineers - Geotechnical
Contractor Sierra Construction Company- (Prime Contractor)
ACC Hurlen (Pile Driving)
Precaster Concrete Technology Corporation, Tacoma, Washington