An expansion and replacement of the U-shaped west end of Husky Stadium at the University of Washington incorporated the use of precast prestressed concrete seating units. Cast as "double" risers, the seating elements have a rise of 16", a run of 30", and a typical length of 43'-46'. A total of 14 new tiers of seating were added in the open air student section of the football stadium.
Products
- 127 pieces - double tread/riser seating units
- 15 pieces - small closure panels
 |
Features
- Prestressing of the seating units allowed for longer spans and increased the bent spacing of the supporting beams.
- The use of double risers, instead of single L-shaped units, reduced the number of joints and installation "picks" for the erector.
- The use of precast stadium units shortened the construction schedule and provided a superior finish to cast-in-place alternatives.
|
Credits
|
Owner |
University of Washington |
|
Designer |
LMN Architects and Skilling Ward Magnusson Barkshire, Inc. |
|
Contractor |
Howard S. Wright Construction Co.
|
|
Precaster |
Concrete Technology
Corporation, Tacoma, Washington
|